Specify Green What you need to know about environmental issues as it pertains to the world of paint & coatings. Covers LEED, color & paint, and our new MPI "Green Performance" approved products list.

   www.specifypaint.com   
Specify Paint Specify Paint Access to what you need to know about paint system choices, paint system surface preparation, approved paint products, painting specifications for both new construction (architectural painting) and maintenance painting.

Architects: Shop Primed Materials
When is too much - too little???

Increasingly, 'challenges' are developing where "temporary coatings" have been applied off-site to products. These products are scheduled to receive paint systems on-site, but had "protective coatings" applied off-site by the fabricator to 'protect' the product. Some of these products include clear-coated glue-laminated beams, chromate-passivated galvanized decking, and shop-primed interior and exterior structural steel.

"Temporary" protective coatings often do the job foreseen by the off-site fabricator, but can cause immense problems to the on-site coating applicator. These problems reflect upon the quality of the specification, as this information is seldom part of the bidding information given to the coatings applicator. Even if the painting specification is of high quality, this action by the steel fabricator may well jeopardize the obtaining of the performance foreseen by the painting specifier. This often results in disputes where there will be "losers", and may well go to litigation. This is in nobody's best interest but the lawyers!

One example is interior and exterior structural steel. Fabricators often take surface preparation information from their portion of the specification - not from the painting portion of the specification. They then apply a 'temporary protective coating' to protect the steel from rust. The steel arrives at the site with a surface preparation which may not be that specified by the design authority for the coating section. It also arrives with the 'temporary protective coating' as a primer!

The dilemma facing the coating contractor and the design authority is that if the coating contractor proceeds with the specified system, it will be on top of the applied 'temporary protective coating'. As with a chain, this 'weakest link' most often results in coating failure. Even if the steel received the specified preparation (generally SSPC - 6), the 'temporary protective coating' still should be removed in order for the specified system to be applied to the properly-prepared substrate.

An example of a 'temporary protective coating' is the standard for "A Quick-drying One-coat Paint For Use On Structural Steel", published in the 1970's as 1-73a by an Institute of Steel Construction, but still in common use today. Close examination of this "Performance Standard" reveals that it is "for use as a single coat on structural steel". It "is intended as a temporary coating of structural steel, or for interior exposures such as dry buildings subjected to infrequent condensation.". It further says that it "is not recommended as a primer in a multicoat system...". The surface preparation requirements call for SSPC SP1 - Solvent Cleaning, and application to a dry film thickness of 1.5 to 2.0 mils. [Note: italics and bolding are ours for emphasis.] The problem is not so much with the standard - but with its application by the fabricator when the architectural painting specification clearly calls for a different level of surface preparation than that called by the standard, and for an appropriate "primer" within the specified paint system. When the steel arrives with the level of preparation and the coating called by the standard being used by the fabricator, what is the coating professional to do? His obligation is to the painting specification, which may well call for a higher level of surface preparation and for an appropriate primer designed for the system that is compatible with the system top coat(s).

Similar conditions sometimes exist with exterior structural steel and steel intended for use in aggressive environments, or environments where moisture or condensation can be a problem.

The MPI is of the opinion that the information in this "Caution Note" should be known by all involved - the design authority, the specifier, the steel fabricator, and the coating contractor. In that way, "challenges" should be minimized in the site coating of off-site prepared steel.

Further information (such as compatibility of coatings and 're-coat windows') is available in the System Evaluation sections (i.e. of interior and exterior substrates) in both the MPI Architectural Painting Specification Manual and the MPI Maintenance Repainting Manual.

The PaintInfo website and contents are copyright ©1996- Master Painters Institute Inc. All Rights Reserved.